Table of Contents Table of Contents
Previous Page  23 / 28 Next Page
Information
Show Menu
Previous Page 23 / 28 Next Page
Page Background

approval of reserved matters, or ‘full’

with all details taken into account.

Both routes require applicants to

provide substantial amounts of

information up-front.

The current process means that

developers and landowners often

have to spend significant time

and resource even to establish

outline ‘in principle’ acceptability of

development. Major proposals that

do not require an EIA are supposed

to take up to 13 weeks to determine

such a principle. However, as most

of us know, the reality is that it often

takes far longer.

By introducing PiP for housing-

led development, the Government is

seeking to increase the efficiency of

the planning process by establishing

more certainty as to whether land is

suitable for new homes.

The intention of doing so is to

separate decision making on ‘in

principle’ issues including use,

location and density/amount from

matters of technical detail such as

materials and what the buildings

will look like.

A grant of PiP would have to be

followed by a successful application

for Technical Details Consent (TDC)

before the applicant could benefit

from planning permission to develop

the site.

Where will PiP be allowed?

Powers secured through the Housing

and Planning Act 2016 allow PiP to

be granted when:

– Local authorities or other

qualifying bodies choose to

allocate housing-led development

in local or neighbourhood plans.

– Local authorities identify land on

their brownfield land registers

(which they are required to set up

under section 14A of the Planning

and Compulsory Purchase Act

2004 once the Town and Country

Planning (Register of Previously

Developed Land) Regulations 2017

come into force).

There may also be the opportunity to

seek PiP directly for smaller schemes

of say 10 units or below that do not

feature in local/neighbourhood plans

or the register. However, this has yet

to be confirmed.

Speeding the principle

It is hoped that PiP will enable the

principle for ‘housing-led’ schemes

to be established within a five week

process, though the subsequent

TDC, which is ultimately what

will be required in order to start

construction, is likely to take longer.

The thinking is that this will allow

some certainty on the acceptability

of the overall use of the site for

housing, appropriate location of

development within the site and

density (possibly within maximum

and minimum parameters).

The exact method by which this will

be achieved is still being determined.

It could be through the wider use of

‘parameter plans’ as a quick way of

identifying those areas within the site

where development is acceptable

and where densification is possible.

Clearly, there will also be a need

to determine the extent to which

such ‘housing led’ schemes can

accommodate other uses. In this

respect it is likely the guidance

will have to provide a judgement,

for example, on the proportion of

housing on site versus other uses,

so that it remains within the spirit

of PiP and compliant with other

elements of Government policy.

PiP’s will also have conditions

attached and potentially be subject

to CIL/S106. As with an outline or full

planning application route, there will be

a right of appeal against any refusal.

Awaiting the details

Much of whether PiP will add to, or

detract from, the existing outline or

full planning permission approach

ultimately rests in the detail due to

be published in spring 2017.

We know that the PiP process is

likely to exempt EIA based schemes,

which could unfortunately cut out

many major housing proposals from

qualifying. A robust approach will

also need to be taken to flooding,

heritage, nature conservation and

traffic at the plan-making stage to

avoid doing it at the PiP stage.

A possible unintended

consequence could be that

developers and landowners have

to ‘front load’ their ambitions by

making sure sites are included in local

plans/brownfield registers. Failing

to do this could invite the risks of

negotiating with parishes as part of

the neighbourhood planning process,

which would defeat the object.

Whether this third way will be the

silver bullet the Government requires

to unlock planning and deliver more

housing growth remains to be seen.

With so many details yet to be

finalised it is very much a case of

watch this space!

By

introducing

PiP for

housing-led

development,

the

Government

is seeking to

increase the

efficiency of

the planning

process by

establishing

more

certainty as to

whether land

is suitable for

new homes

CUSHMAN & WAKEFIELD

23

#TRENDING